Space Layout

Space Status

We are officially out of the old location.

Unfortunately the electrical permit process and work has taken longer than we expected. All the conduits are complete, but without wiring and meters, we can’t do much, even if we wanted to.

What must be done:

1. Finish Electric

2. MECO installs meter.

3. County electrical inspection.

4. County issues occupancy permit.

We are targeting a soft opening between 1 Oct and 15 Oct, but the only time line under our direct control is finishing the electrical.

In the meantime, our volunteer members will be setting up the workstations and equipment, and decorating the space. Please check out our calendar hereEvents Calendar and pitch in if you can.

The warehouse is 3000 sq ft, but a commercial CNC occupies about half the space. We think this will be a good fit for Maui Makers.

 